Project management is a wonderful art of managing different tasks and various task dependencies , material , people , funds and information.

Reddemy may receive an affiliate commission if you enroll in a paid course after using these buttons to visit Udemy. Thank you for using these buttons to support Reddemy.

Taught by
Amey Vidvans

Reddit Posts and Comments

0 posts • 2 mentions • top 1 shown below

r/excel • comment
1 points • IAmey

Hello ,

Please try following steps.

Step 1 - Insert Chart

  1. Select Start dates > Go to Insert tab > Under charts > Select 2D stacked bars.

step 2 - Add horizontal Axis labels.

  1. select chart > Right click and click on select data.
  2. select start series > Under horizontal Axis label > click on edit > Select Activity list.

Step 3 - Add duration series.

  1. on the left hand side click on add.
  2. select durations
  3. under horizontal Axis labels again select Activity list.

Step 4 - Format Vertical Axis.

  1. Select Axis > Right click > format Axis > Go to Axis option > check categories in reverse order.

Step 5 - Format Horizontal Axis.

  1. Select Horizontal Axis. > Right click > format Axis.
  2. Under Axis Option-
  3. Under bounds- this will define start and finish of your Timescale or Timeline.
  4. Under minimum Enter date less than your start date of first activity.
  5. Under maximum Enter date greater than finish of your last activity.

Step 6 - Hide start Series.

  1. select Start series bars.
  2. Go to format > No fill and no outline.

Please check if this helps. Please revert in case you need further assistance.

You may refer !

With warm regards.