Learn PMP Math EVM Concepts in 1 Hr to Dominate the PMP Exam

share ›
‹ links

Below are the top discussions from Reddit that mention this online Udemy course.

Are you apprehensive about all the math problems on the PMP exam? Like thinking about doing math instantly transports you back to being an awkward high school student that dreaded going to algebra class? It’s not particularly pleasant to think about.

Reddemy may receive an affiliate commission if you enroll in a paid course after using these buttons to visit Udemy. Thank you for using these buttons to support Reddemy.

Taught by
Garrett Heath

Reddit Posts and Comments

0 posts • 1 mentions • top 1 shown below

r/pmp • post
12 points • CluelessMN
I am a PMP! (5xAT)

I just passed today! Here is what I did to prepare.

I applied last October and put off the test a couple of times due to other obligations. The fire was lit when I realized I only had a couple more months left before my year window was to expire. I planned to read a chapter from the PMBOK and then watch the corresponding section from Joseph Phillips’ Udemy course, PMP Exam Prep Seminar - PMBOK Guide 6, one chapter per two days. It didn’t go exactly as planned and it ended up taking a whole month to finish. I also took the quizzes from Udemy and took 30-40 custom exams from Pocket Prep per section.

After I completed the PMBOK and Udemy course I started reading "PMP Exam Prep Simplified" by Andrew Ramdayal. I tried to do one chapter a night along with the quizzes. Some days I just wasn’t able to fit in studying so this also took longer than anticipated. I really liked the book, it was an easy read.

I also bought an EVM course on Udemy. Learn PMP Math EVM Concepts in 1 Hr to Dominate the PMP Exam by Garrett Heath. I would highly recommend if you are worried about remembering the formulas. I also watched the Vargus video twice to help understand the correct flow of the 49 processes.

I started practice exams about a month before my exam. I had planned to use multiple sources for my practice exams, but after reading that Prepcast was the preferred choice, I stuck with Prepcast. I had also planned on taking 12 practice exams. I quickly found out I didn't have time to fit this is. It was too difficult for me to schedule 4 hours outside of work and kids. In the end I did three practice tests (74.5%, 73.5% and 83%). After getting 83% less than a week until the exam I decided I didn’t want to take anymore. My confidence was high and I didn’t want to risk getting a lower score and having my confidence decrease.

Here are some non-study exam prep that I did.

  • I took 4 days off before my exam to focus on studying. I did a lot less studying than I intended, but it was nice to focus on the material in the mornings and not have work stress on top.
  • The day before I did minimal studying. I got a neck and shoulder massage at the mall and drank some de-stress tea.
  • I went to bed at 9:30 and took some melatonin to help me fall asleep.
  • It was tempting to roll out of bed and take the test in sweatpants, but I decided to feel confident I needed to look nice. I wore jeans and a cardigan and did my hair and makeup. 
  • Before I went into the building I did a power pose for two minutes. It felt silly, but anything to help me stay confident was my goal.
  • I took the first 10 minutes to write down all the processes and formulas. I think the act of doing it helped my confidence level by showing myself I knew what I was doing.

I have a few items that I’m no longer using. PM if you are interested.

  • PMP ExamPrep Simplified: Based on PMBOK® Guide Sixth Edition by Andrew Ramdayal – $20
  • PMBOK Sixth Edition – $30
  • Prep Cast Simulator (active until December 14th) - $90
  • BrainBok PMP 5-Exam Pack (active until November 14th) - $40 (I took a practice exam through this when I started studying last year. I panicked and bought Prep Cast, but now looking back at the practice test I took, I think I could have continued with BrainBok.